Jira & Confluence Data Center to Cloud Migration Guide (4/5)

Phase 4: Production Migration

This is the final move — the transition from Data Center to Cloud. The goal is a smooth cutover with minimal disruption, using the precision gained from your test migrations. The focus now shifts to coordination, risk management, and execution.

This phase includes three key steps:

  • Prepare & Lift and Shift
  • Users Preparation
  • Run Migration

At this stage, everything has been tested, cleaned, and scripted — now it’s time to execute.

4.1 Prepare Lift & Shift

By now, you’ve tested everything, fixed what was broken, and scripted what could be repeated. Now it’s time to bring all that preparation together and execute it for real. This step is about getting everything and everyone ready for production cutover. That means creating clear documentation, aligning all stakeholders, booking your migration window, and notifying Atlassian. It’s the moment your migration plan becomes a live operation.

4.1.1 What do I need to prepare?

There are two essential assets you need: a Runbook and a Migration Execution Plan.

The Runbook is your technical instruction manual. It should be detailed enough that any engineer on your team could follow it step by step without needing to ask questions. If a task involves running a SQL script, the runbook should specify the exact query, required permissions, server location, and how to validate success. If a Groovy script is involved, link directly to the repo or embed the code using an extendable Confluence macro.

At WiQU, we usually create a dedicated Confluence space inside the customer’s new Cloud environment to manage the migration. This not only centralises all runbook documentation but also introduces stakeholders to Confluence Cloud in a natural, productive way — because we’re already using it together.

Your Execution Plan complements the runbook. It’s a simplified timeline table that clearly lays out who does what, when, and how long it should take. This plan is especially useful for aligning with non-technical stakeholders — it gives them a sense of timing, ownership, and impact. We keep it simple for clarity: Date and Time, Duration, Action, Owner, and a short description. Example:

4.1.2 What about the maintenance window?

Once your plan is ready, make sure it fits into a maintenance window that’s agreed upon with all stakeholders. This is key for reducing user disruption and ensuring resource availability. In most cases, we schedule production migrations over the weekend — usually Saturday evening into Sunday — to avoid interfering with business operations. Just remember: the more time you have for post-migration validation, the better.

4.1.3 Do I need to communicate with Atlassian?

Absolutely. Atlassian’s support team can actively assist during your migration — but only if they know about it ahead of time. We recommend raising a support ticket at least two weeks before your go-live date, especially for large migrations, JSM Assets, or known Confluence macro issues. Include your timeline, project/space volume, and any expected risks. They’ll coordinate with you behind the scenes and, when needed, run their internal repair tools during your cutover.

4.1.4 How do we reduce risks?

This is where your runbook becomes your insurance policy. Every step you tested in UAT should now be documented — with updated timings, stakeholder notes, and fallback options. If you used a staging environment during UAT, consider refreshing it with a current production backup and running one final dry-run. This last rehearsal can catch unexpected changes that may have slipped through.

Also, make sure your runbook and execution plan include all post-migration manual steps — things like re-linking apps, reconfiguring integrations, or reapplying permissions. The fewer assumptions, the fewer surprises.

4.2 Users Preparation

The migration itself might only take a few hours, but preparing your users for the change is what determines whether you’ll get flooded with support tickets or receive positive feedback. This step is all about education, communication, and expectation management. Your Jira and Confluence may technically be the same tools in Cloud, but the experience is very different.

We aim to make users feel confident the moment they log in after cutover. That means hands-on walkthroughs, clear communications, and making sure admins and end-users alike are aware of what’s changed — and why it’s better.

4.2.1 Is Cloud the same as Data Center?

Quick answer: absolutely not.

Yes, Jira Cloud and Jira Data Center share the same core concepts — projects, issues, workflows, permissions — but the UX, admin structure, and overall user experience have evolved drastically. Think of Cloud not as an upgrade, but a completely different product that happens to speak the same language.

Atlassian has introduced well over 1,000 new features in Cloud that do not exist in DC — from automation templates to smart links, advanced dashboards, and deep integrations with tools like Slack, Google Drive, and Loom. Even simple things like where to find buttons or how to assign a user are often different.

Don’t assume people will “figure it out.” Even seasoned users can get lost in the new UI.

4.2.2 Do users need training?

More than recommended — it’s essential.

Yes, Atlassian offers great courses through Atlassian University, but let’s be honest — how many of your users are actually going to read through documentation or complete an online course on their own?

At WiQU, we include custom training sessions tailored to each client. We don’t just show where buttons moved — we explain why Cloud works differently and how to take advantage of new features. That means fewer “false” bug reports (“my board is gone!”) and more confident teams who are ready to get to work.

Want to reduce support tickets post-migration? Train your users.

Want to actually unlock the value of Cloud? Train your users.

4.2.3 What about Jira admins — do they need training too?

Yes — and ideally, they should already be part of your migration squad.

The best way we ensure knowledge transfer with Jira admins is by involving them in the migration itself — assigning them tasks, showing them how Cloud tools work in real time during the migration. But even so, we recommend scheduling a dedicated session post-migration to walk through the key changes.

This includes:

  • Where and how to take backups in Cloud
  • How user management works (via admin.atlassian.com)
  • Understanding organisations, sites, and the new permissions model
  • Managing apps, billing, and new audit tools

Whether or not your instance is connected to Atlassian Access, Cloud centralises identity and organisation management — and Jira admins must be aware of that shift.

4.2.4 What should users know?

Timing is everything. It’s best to notify users after UAT has been successfully completed — when you’re confident about dates, scope, and stability.

Here’s what we recommend sharing:

  • Migration date and time
  • Expected downtime (if any)
  • What will change and what won’t
  • Quick links to help docs or internal guides
  • Who to contact for questions

Bonus tip: create a “Welcome to Cloud” Confluence page where you explain the top 5 things that changed and include screenshots, video walkthroughs, and links to raise support tickets. Make it easy, visual, and human.

4.3 Run Migration

This is the moment everything leads up to: the actual production migration. You’ve planned, prepared, tested, trained, and aligned your team. Now it’s time to execute your lift and shift using the Cloud Migration Assistant (JCMA or CCMA) — but this time, it’s with real data, real users, and real consequences.

The focus here is precision, communication, and control. Nothing new should happen — if you’ve followed the process, everything you’re doing now has already been rehearsed in your test migrations.

4.3.1 What do I need to do during migration?

First, make sure your production instance is in read-only mode to prevent any last-minute changes. Locking down the environment ensures the snapshot you’re migrating remains consistent.

From there, execute your runbook step by step. Stick to the timeline in your execution plan, log what’s done, and note any delays or deviations for post-mortem review. It’s not unusual for the migration assistant to take several hours to complete, depending on the number of projects, attachments, and apps.

If you’re running additional scripts (like app data migration or custom REST API calls), make sure they’re queued in your runbook with exact timestamps and validation checks. Your Cloud site should be monitored during the import to catch any early errors or timeout warnings.

4.3.2 How long does it take?

That depends on your instance size and complexity — but your test migrations should already give you a very close estimate. In our experience, a typical production migration might take:

  • 3–8 hours for small or medium-sized Jira instances
  • 8–14+ hours for enterprise setups, especially with heavy attachments or Assets

Add extra time for post-import validation and configuration steps like app setups and permissions review. That’s why we recommend starting in the evening and using overnight or weekend hours to give yourself breathing room.

4.3.3 Can I monitor progress?

Yes — and you should.

The migration assistant shows status updates in the UI, but don’t rely solely on that. If possible, have someone tailing the logs on your Data Center instance and checking Cloud import logs through Atlassian’s admin interface or support. If you’ve raised a support ticket in advance, Atlassian may also provide insight in case of issues.

4.3.4 What if something goes wrong?

That’s why you prepared a rollback and contingency plan.

If a major blocker appears (for example, app data failed, key permissions didn’t copy, or workflows are broken), your options include:

  • Restoring a backup of your Cloud site
  • Re-importing with fixed data
  • Rolling back to Data Center and rescheduling the cutover

Ideally, none of this happens — but your migration plan should include a “no-go threshold” and fallback steps just in case. Always communicate your status with the team and stakeholders, even if things are going well — silence during a migration can create unnecessary panic.

4.3.5 How to do it?

Keep it simple — just follow the same approach you used during UAT, but with a few key extras:

  • Create a fresh backup of your production database before starting. Even if you are executing from a staging environment, make sure both your on-premise and Cloud environments are backed up. (A Cloud backup article is coming soon.)
  • Set all your Jira projects and Confluence spaces to read-only mode. This prevents last-minute data changes and ensures consistency. (We’ll publish a guide for this soon.)
  • Finally, execute the same runbook you tested during UAT. The process should be familiar by now. If you missed it, here’s the full walkthrough in our article Phase 3: Test Migration & UAT

Conclusion

Phase 4 is the most visible part of your migration — the moment teams see the result of months of preparation. But a smooth cutover doesn’t happen by luck. It takes coordination, training, rehearsals, and clear communication. The teams that succeed are the ones who test thoroughly, document every step, and prepare users for the change. With a detailed runbook, a reliable execution plan, and empowered power users, your move to Atlassian Cloud can be smooth, predictable, and even celebrated.

Articles Related

Let us know what you need and get up to 2 days of consultancy at no cost

Browse guides, templates, and how-tos we’ve published for public use

Just want to talk? – Scroll down, pick a time that suits you, and let’s chat.

Sign Up for Updates and Access to the WiQU Portal

Register on our portal to receive the latest updates, training resources, and access to support tools designed to enhance your experience.

WiQU
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.