A Project Manager’s Guide to Migrating Jira and Confluence from Data Center to Atlassian Cloud

You’re not just migrating tools. You’re changing how people collaborate, how work flows, and how your organisation scales. That shift needs more than scripts or assistants — it needs real project management discipline. And it starts with the right delivery model.

In our recent migration for a 500-user company, timelines were tight, dependencies ran deep, and the risks were real. We delivered it using a hybrid methodology that blends traditional governance with agile execution. Here’s how that played out — and how you can do the same.


Waterfall & Kanban: Why Hybrid Wins for Cloud Migrations


Migration projects are a different beast compared to product launches. While product teams can pivot and iterate freely, migrations are infrastructure-heavy, scope-fixed, governance-sensitive, and riddled with dependencies that demand meticulous coordination. This is why a hybrid delivery model works best. We use Waterfall for planning, approvals, and documentation – ensuring rock-solid governance, risk management, and stakeholder alignment before any data moves. Then, once execution begins, Kanban takes over to drive iteration, testing, and continuous monitoring. This approach delivers the best of both worlds: structured control upfront and real-time agility during execution, allowing teams to adapt quickly without compromising quality or compliance.

Step 1: Start with a Real Technical Assessment

Step one in any successful Atlassian Cloud migration is a thorough technical assessment – your true north for everything that follows. This is where your Solution Architect and Project Manager join forces to run a deep-dive review of your existing Jira and Confluence environments. In Jira, assess projects, workflows, custom fields, screen schemes, and permission structures. In Confluence, look at spaces, page templates, macros, and overall content sprawl. Don’t forget the Atlassian Marketplace apps – are they cloud-compatible?

Many apps in Atlassian’s Marketplace behave differently in the Cloud – and some don’t exist there at all. Even for apps that do have Cloud versions, the feature set, data storage, or licensing model may have changed significantly. What worked in Data Center might need reconfiguration, replacement, or complete retirement in Cloud.

To manage this risk, your Statement of Work should include language like:
“Client to review Cloud app compatibility and approve replacement decisions.”

This keeps responsibility and decision-making aligned between delivery and the business, and avoids late-stage surprises. For each app, define the migration path: Will it be migrated manually? Will the vendor assist? Or will you replace it with a native Cloud feature or another tool entirely?

 

Step 2: Create a Statement of Work that Protects Everyone

 

The Statement of Work (SoW) is the backbone of your migration project. A well-crafted SoW defines what’s in scope, what’s out, and how the team will be held accountable throughout the engagement. It brings clarity to all parties involved and creates alignment before a single line of data is moved.

Here’s what every migration SoW should include: in-scope systems such as Jira Software, Confluence, and any relevant Atlassian Marketplace apps approved for Cloud. Just as important is what’s not included, such as non-Atlassian systems, legacy data archives, or unsupported third-party apps.

Include assumptions that keep the scope honest. For example: “Client will assign UAT testers by (a specific date)” or “All project data will be made available prior to staging.”

Key deliverables may include the migration plan, test scripts, access provisioning details, staging environment setup, and the final migration report. Define your change control process, how changes to scope will be managed, reviewed, and approved. If applicable, outline your payment schedule, especially where external vendors are engaged. And of course, break down your timeline into phases with milestones and stakeholder sign-offs to give the project structure and rhythm.

Capacity planning should be reflected here as well. Your SoW must realistically account for team availability during UAT, content validation, approvals, and other key project activities. Overlooking this can result in an ambitious plan on paper but a slow, fractured execution in reality. Build your timeline around real availability, not just ideal effort hours.

Your RACI matrix becomes especially useful in this phase. By assigning clear roles and responsibilities for deliverables, such as staging setup, UAT coordination, or configuration validation, you prevent finger-pointing midstream and keep accountability crisp. Everyone knows what they own, what they support, and when they’re needed.

Equally important is incorporating a basic quality plan into the SoW. Define what quality looks like for this migration: does it mean that every issue type must carry over with its full history intact? Does it mean 100% test pass rate on smoke testing? Establishing your quality standards early ensures everyone is aligned on the definition of success and prevents scope creep disguised as “fixing defects” later on.

Step 3: Track Risks with a RAID Log You Actually Use

Great project managers don’t just track risks – they make them visible, scored, and actionable. A RAID log is your essential tool for doing that. It helps you stay ahead of issues by clearly documenting four key dimensions: Risks, Assumptions, Issues, and Dependencies.

For example, a high-risk item might be that a critical app isn’t Cloud-compatible. You’d flag this early, mark it as a high-likelihood, high-impact risk (red status), and present some alternative applications to the customer.

Each risk should have a clear owner and a concrete mitigation action. Track this log weekly and use it in sprint reviews, PMO check-ins, or steering committee meetings to drive informed decisions.

Step 4: Use Tools That Give You Control, Not Just Data

Once the migration is underway, visibility becomes everything. Teams need to know what’s in flight, what’s blocked, and what’s next – while executives need a higher-level view of progress, risks, and ROI. The right tooling gives you both.

Start with Jira as your day-to-day execution engine. Set up a Kanban board with clearly defined Epics that map to the major phases of your migration: Discovery, Data Clean-Up, Dry Run, UAT, Go-Live, and Hypercare. Use swimlanes to organize work by phase or stream, and apply Work in Progress (WIP) limits to avoid overloading your team.

To monitor performance, configure a Jira dashboard with key delivery metrics. Track cycle time, lead time, and time in status to understand where work is slowing down. Monitor blocked issues to proactively resolve bottlenecks. If you’re running a formal UAT process, a burndown chart showing signoffs can provide daily insight into progress.

To get deeper insights, consider improving your dashboard with Marketplace gadgets. Tools like Time in Status by OBSS can give you granular visibility into task delays, while Gantt for Jira Cloud helps stakeholders understand the broader timeline and dependencies.

For executive-level reporting, Power BI is a great complement to Jira. Build a real-time dashboard that surfaces RAID log summaries by RAG status, tracks Epic completion over time, and shows actual cost versus forecast.

To feed Power BI with Jira data, use the Jira REST API or connect via a plugin like Power BI Connector for Jira. Once integrated, you’ll have a living source of truth that both teams and leadership can trust.

Step 5: Align Identity Early or Risk a Last-Minute Blocker

User identity issues are a common blocker in Atlassian Cloud migrations. On-prem setups often allow duplicate or outdated accounts – but in Cloud, email is a unique identifier, and that flexibility disappears.

One frequent issue is having the same email tied to multiple accounts, or former users still linked to issue history. These conflicts can break user provisioning and delay your migration.

To avoid this, audit your user base early. Remove duplicates, and assign placeholder emails to former users to preserve history without causing conflicts.

Just as important: communicate these changes to your teams. Transparency helps avoid confusion and ensures smoother testing and rollout.

Let us know what you need and get up to 2 days of consultancy at no cost

Browse guides, templates, and how-tos we’ve published for public use

Step 6: Own the Testing Milestone Like a Launch

A successful migration isn’t just about moving data – it’s about ensuring everything works as expected in the Cloud. Functional and permission testing are just as important as verifying that the data arrived.

For Jira, a solid UAT checklist should include:

  • Field-level accuracy (text, select lists, dates)

  • Comments, attachments, and issue history

  • Workflow integrity and transition behavior

  • Filters, dashboards, and subscriptions

  • Notifications and automation rules

  • Correct application of permission schemes

For Confluence, focus on:

  • Page formatting and macro rendering

  • Internal and Jira-linked page references

  • Permissions, restrictions, and access control

  • Archived spaces and template availability

Where possible, automate the heavy lifting. Tools like ScriptRunner, Xray, or QTM4J can help you verify configurations, test scripts, and user behaviors at scale.

Thorough testing ensures more than just data integrity – it validates usability, access, and readiness for go-live.

Step 7: Close Like a Pro

After go-live, it’s tempting to shift focus immediately to the next initiative – but strong project closure is what turns a successful migration into a sustainable transformation. It’s also your moment to lock in learnings, celebrate progress, and ensure long-term adoption.

To wrap the project with confidence, focus on a few key deliverables:

Start with a Final Summary Report that compares scope versus actual delivery, highlights key issues resolved, and captures feedback from stakeholders and end users. Ensure access provisioning is complete, and that all active users are verified and fully enabled in Cloud.

Next, formalise the support handoff. This includes runbooks, support contact lists, and documentation that internal teams can rely on post-migration. Stakeholder and client sign-off should also be recorded to officially close the project phase and start your operational transition.

Finally, run a retrospective. Capture what worked, what didn’t, and what to improve next time. If possible, collect reviews or testimonials – especially if the migration improved performance, security, or team workflows.

And don’t forget to celebrate. You’ve just executed a high-stakes, high-impact digital transformation.

Migrating to Atlassian Cloud reshapes how your teams work and grow. As the Project Manager, you guide that journey, balancing structure with agility every step of the way.

Plan smart, deliver in small wins, and close with clarity.

Follow us for more project management insights – and feel free to reach out if we can help in any way.

Final Words

Migrations are transformations. They don’t just move data — they reset the way teams work, scale, and collaborate.

At WiQU, we bring technical expertise and delivery precision to every engagement. Whether you’re running a 20-user setup or a 5,000-user enterprise, our team helps you plan smart, migrate safely, and land cleanly in the Atlassian Cloud.

If you’re preparing your own migration, we offer a free 2-day discovery to help you scope, sequence, and de-risk the journey.

Get in touch: info@wiqu.io

Just want to talk? – Scroll down, pick a time that suits you, and let’s chat.

Sign Up for Updates and Access to the WiQU Portal

Register on our portal to receive the latest updates, training resources, and access to support tools designed to enhance your experience.

WiQU
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.